MICRO GENERATORS ≤10kW
Distributed Energy Resources (DER) include solar panels, combined heat and power plants, energy storage facilities, and natural gas-fueled generators.
Our Engineering Department assesses and approves the connection of all DER connections to our distribution system.
1 MICRO DER APPLICATION
First, complete and submit the application found below.
2 ENGINEERING TECHNOLOGIST SITE VISIT
Grimsby Power will review the application and, once it is accepted, a Technician will visit the proposed installation site to gather information to put together the Offer to Connect/Service Layout.
3 Micro embedded CONNECTION AGREEMENT AND OFFER TO CONNECT/SERVICE LAYOUT
Grimsby Power will issue a Connection Agreement and Offer to Connect which outlines the requirements and Grimsby Power’s costs to connect the generator. If you decide to proceed with the project, you will be required to pay the connection fees detailed in the Offer to Connect/Service Layout.
Micro Embedded Generation Facility Connection Agreement
4 DESIGN & BUILD
Once the micro generation facility has been built according to our requirements, you will need to apply to the Electrical Safety Authority for an electrical inspection.
5 FINAL CONNECTION
Grimsby Power will schedule a meter change to install the new bi-directional meter. Grimsby Power will also do the necessary work to ensure billing arrangements are set up based on the project type.
Technical Requirements
Grimsby Power follows the most recent version of the Hydro One TIR for technical interconnection requirements of DER:
https://www.hydroone.com/business-services/generators/technical-requirements
Small, Mid-Sized and Large Embedded Generators >10kW
Distributed Energy Resources (DER) include solar panels, combined heat and power plants, energy storage facilities, and natural gas-fueled generators.
Our Engineering Department assesses and approves the connection of all DER connections to our distribution system.
1 PRELIMINARY CONSULTATION INFORMATION REQUEST
The first step is to complete and submit Preliminary Consultation Information Request. Grimsby Power will respond to this request and provide you with the connection details for the proposed project and outline the available capacity. At this time, Grimsby Power will also provide details for a Connection Impact Assessment through a Preliminary Consultation Report.
Preliminary Consultation Information Request (PCIR & PCR)
2 CONNECTION IMPACT ASSESSMENT APPLICATION
After the preliminary consultation, complete and submit a Connection Impact Assessment Application complete with payment as per the CIA Study Fee Schedule.
GPI Connection Impact Assessment Form
3 CONNECTION IMPACT ASSESSMENT
Grimsby Power and any other affected Utility will perform a Connection Impact Assessment for the proposed generator. Grimsby Power will then issue the report(s) once they are complete. You will be allocated capacity on the grid upon completion of the Connection Impact Assessment by all Utilities involved.
Please Note: For generators connecting on a Utility shared feeder, that utility maybe required to perform its own Connection Impact Assessment. Details of Utilities involved will be provided during the Preliminary Application stage.
4 CONNECTION AGREEMENT/OFFER TO CONNECT
Grimsby Power provides you with a Connection Agreement for your proposed Generator. Included in the Connection Agreement is a Connection Cost Agreement. This Connection Cost Agreement serves as your Offer to Connect and provides a cost estimation specifying the scope of work to be performed either by you, Grimsby Power, or Upstream Utilities, in order to make the generation connection.
If you decide to proceed with the project, you must sign the Connection Agreement, sign the Connection Cost Agreement, and make the required payments.
GPI Small Mid Sized Embedded Generation Agreement Sample
5 DETAILED DESIGN REVIEW & CONTRUCTION
You will be required to submit a Detailed Design Review to ensure all requirements for the connection have been satisfied. Grimsby Power will review the Detailed Design and provide feedback and/or approval.
Once the final design is approved you must complete the construction of the generation facility and then apply to the Electrical Safety Authority for an electrical inspection.
Concurrently Grimsby Power and the Upstream Utility (if required) will perform the necessary work required for the connection.
6 COMMISSIONING & CONNECTION
You will be required to complete and submit a Commissioning Plan and Commissioning Verification Report.
Depending on the Scope of the project, Grimsby Power may want to witness the commissioning activities.
After the Electrical Safety Authority provides us with the electrical inspection "Connection Authorization", Grimsby Power will connect the generator to our Distribution System to allow for completion of the commissioning activities.
7 FINAL AUTHORIZATION
Once all requirements and commissioning activities have been approved by Grimsby Power, we will issue an authorization letter that permits the generator to operate within the parameters of their connection agreement.
8 SUPPORT
As DER connections vary in scope and complexity, Grimsby Power will work closely with you during the entire project from application through commissioning.
Technical Requirements
Grimsby Power follows the most recent version of the Hydro One TIR for technical interconnection requirements of DER:
– https://www.hydroone.com/business-services/generators/technical-requirements
Restricted Feeders
There are currently no feeders that Grimsby Power operates that do not have short circuit capacity to accommodate a generation facility connection.
For more information about the 2023 supply mix please click here.
READ ALL ARTICLESFor more information about the 2023 supply mix please click here.
Learn MoreGrimsby Power filed an IRM application with the Ontario Energy Board (OEB) on August 15, 2024 ...
Learn MoreYou could get a monthly, on-bill credit of $35 or more ...
Learn MoreGrimsby Power has been notified that individuals representing themselves as a utility responsible for providing power a ...
Learn MoreThe Ministry of Energy is responsible for providing Ontario’s electricity supply mix data for electricity suppliers ...
Learn MoreOn August 17, 2023, Grimsby Power filed an IRM application with the Ontario Energy Board (OEB) to change rates effective ...
Learn MoreThe following rates apply to the Electricity line on your bill: Winter Time-of-Use TOU On-Peak 18 ...
Learn MoreGrimsby Power is introducing a new customer account portal ...
Learn More